Georgia index · last changed 18 September 2026
Georgia data centers: what the public record shows.
Selected source-linked records are published below. This is not a complete inventory of Georgia data centers.
Explore Georgia
Map, listings and checked facts.
Start with 58 licensed source leads, then inspect the separate public-evidence layer below. Licensed rows are not independently verified and are not a statewide census.
Georgia map
Reported locations in Georgia
58 licensed rows · 38 source localities · 4 map targets
Browse 4 mapped areas as links
- Douglasville area31 source localities · 51 licensed rowsAdairsville, Alpharetta, Atlanta, Austell, Cartersville, Conyers, Covington, Dalton, Douglasville, Ellenwood, Fayetteville, Gainesville, Griffin, Jackson, Kingston, LaGrange, Lithia Springs, Lovejoy, Marietta, Maysville, Moreland, Newnan, Norcross, Palmetto, Rome, Social Circle, South Fulton, Stilesboro, Temple, Tyrone, Villa Rica
- Appling area3 source localities · 3 licensed rowsAppling, Augusta, Evans
- Blakely area2 source localities · 2 licensed rowsBlakely, Columbus
- Rincon area2 source localities · 2 licensed rowsRincon, Statesboro
Map sources and method
The state outline is adapted from the U.S. Census Bureau 2025 cartographic boundary file. Facility coordinates are adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Outline and markers use one geographic projection before any explicitly disclosed readability offset. Exact singleton source anchors are never moved. A one-kilometre boundary tolerance prevents the simplified 1:20,000,000 outline from hiding legitimate border-area source points; farther conflicts are disclosed, not clamped. DataCenterData groups source-reported city coordinates only within a bounded map radius; the outline does not validate a facility record.
Browse all 58 rows below. Licensed rows are not independently verified and remain separate from the checked public-evidence layer.
-
1155 Powers Ferry Place Data Center (Prime Storage conversion)
Prime Storage (Prime Group Holdings) — end user undisclosed
1155 Powers Ferry Place · Marietta · Cobb County · Georgia
source-reported permittedPlanned 18 MWSource updated 10 September 2026approximate locationView facility →dcd-dir-001151 -
Aligned Data Centers ATL-01
1551 N River Road · Lithia Springs · Douglas County · Georgia · 30122
source-reported operationalCapacity not statedSource updated 28 August 2026approximate locationView facility →dcd-dir-000031
Georgia evidence at a glance
Some questions answerable
Selected public evidence, not a statewide census. Each row shows whether it is independently source-linked, attributed, or unresolved; licensed leads remain separate.
- Published project / campus
- 8
- Published facility / building
- 0
- Attributed or unresolved rows
- 0
- Licensed directory leads
- 58 not independently verified
- Capacity boundary stated
- 0 of 8 published DataCenterData rows
- Review timing
- Audit through 17 September 2026 · next 17 November 2026
Neither DOR document names a recipient, so no exemption certificate holder could be identified.
Browse all 58 Georgia licensed leads → · Why these counts differ →
Projects
8 project records. Names are as they appear on each record page.
| Microsoft Tyrone Data Center Project | approvedproject | UnknownNo independently supported figureNo primary-source critical IT, utility-service, generation or measured-load figure was established. | Microsoft Data Center Project Information — Town of Tyrone →Gov. record |
| Project Camellia | proposedproject · Georgia DRI 4801; initial information filed 22 July 2026; regional-review status is not project lifecycle status. | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
| Project Sail | proposedproject · Georgia DRI 4361 initial filing dated 31 December 2024; proposed rezoning basis only. | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
| QTS - Blakely | proposedproject · Georgia DRI 4651; initial form filed 10 March 2026; additional form recorded 16 September 2026. | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
| Kingston Technology Hub | proposedproject · Georgia DRI 4835; initial form filed 4 September 2026; proposal and regional-review records only. | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
| ATL2 East | approvedproject · City of Fayetteville Ordinance 25-O-34 adopted 18 December 2025 (rezoning). Zoning approval only — not construction or operation. | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
| ATL50 | proposedproject · Georgia Department of Community Affairs (DCA); Initial DRI Information Form, DRI #4843, 'Brief Description of Project'; action requested checkbox = Permit; 'other action' = Masterplan Review; document date 2026-09-15 | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
| Gregory Road Data Center | proposedproject · Georgia Department of Community Affairs (DCA); Initial DRI Information Form, DRI #4428, 'Brief Description of Project'; requested actions = Rezoning and, under 'Other', 'Annexation'; document date 2025-03-27. Newton County Board of Commissioners Resolution R050625, adopted 2025-05-06, objects to the annexation application under O.C.G.A. § 36-36-113. Lifecycle remains 'proposed': DRI process status 'Completed' is the state review process closing, not local approval, construction or operation. | UnknownNo independently supported figure | Georgia Department of Community Affairs (DCA) →Gov. record |
Where the records were checked
Statewide audit pending
Enough to answer questions
This is still not a list of every data center in the state.
Statewide coverage is not complete. The records below are sourced; a full statewide count has not been published.
State research audit window ended 17 September 2026. Individual records and claims below show their own evidence dates and may be newer.
Next scheduled review: 17 November 2026.
8 independently source-linked project/campus records; 0 independently source-linked facility/building records; 0 attributed or unresolved rows. These counts use different units and must not be added together.
Source families checked, selected records and remaining gaps
These notes name selected records, say which kinds of public evidence were checked and show what remains missing. They do not add anything to the published counts.
- economic development incentives — Checked
- Neither DOR document names a recipient, so no exemption certificate holder could be identified.
- The earlier (pre-May 9 2022) county table linked on the same page was not yet reviewed directly.
- A statewide DRI keyword sweep of every data-center row was not published; selected DRI initial forms and summaries were later opened for Project Camellia, Project Sail, QTS - Blakely and Kingston Technology Hub.
Selected records
- Data Centers Sales & Use Tax Exemption - Aggregate Expenditures by County · Georgia Department of Revenue
- High-Technology Data Center Minimum Investment Thresholds by County (effective on or after May 9, 2022) · Georgia Department of Revenue
- utility commission large load — Partly checked
- No searchable Georgia PSC docket URL was exposed, so docket 44280's full filing list and any Georgia Power IRP or large-load report were not enumerated.
- The order PDFs could not be read (image-only scans, no OCR performed), so nothing is quoted from the orders themselves.
- Georgia Power's Integrated Resource Plan, its large-load queue reporting and any electric service agreements were not retrieved; no research lead has a utility_request_mw figure.
- Several research leads are described as having applied to Georgia Power for specific loads (for example a 99 MW maximum at Statesboro and a 288 MW grid connection at Cartersville); none of those applications was located.
Selected records
- Document Filing #221165 — Order Approving Revisions to Georgia Power Company's Rules and Regulations, Docket 44280 · Georgia Public Service Commission
- Document Filing #222325 — Order on Georgia Power Company's Revision to Rules and Regulations Tariff Compliance Filing, Docket 44280 · Georgia Public Service Commission
- Georgia Public Service Commission home page · Georgia Public Service Commission
- environmental construction permits — Partly checked
- GEOS was unavailable during review; no Georgia air permit application or issued permit was retrieved.
- The Georgia EPD air-quality permit reported issued for Serverfarm on 2026-06-29 and the 2026-07-02 Notices of Violation were not retrieved from EPD.
- The Georgia EPD reference SAS-2024-00075 associated with the DC BLOX Rockdale campus was not retrieved and is recorded only as a note.
- No water withdrawal, stormwater or county land-disturbance permit was searched for any research lead.
Selected records
- Air Protection Branch Forms and Permits · Georgia Environmental Protection Division
- Georgia EPD Online System (GEOS) · Georgia Environmental Protection Division
- Georgia EPD public notices index · Georgia Environmental Protection Division
- municipal planning assessor gis — Partly checked
- Effingham County's Project Camellia page did not respond during review twice; the bounded public record now rests on the Georgia DRI filing rather than that county page.
- Coweta County's zoning case system was not reached, so Project Peach, Project Oak and Bridgeport still have no county record; Project Sail now has a Georgia DRI filing but not a county rezoning decision.
- No Bartow, Spalding, Douglas, Newton, Floyd, Carroll, Fulton, Rockdale, Richmond, Columbia, Hall, Muscogee, Troup, Early, Bulloch, Clayton or Cobb agenda, minutes or zoning file was retrieved; selected Georgia DRI filings were later opened for Kingston Technology Hub and QTS - Blakely.
- Only one Georgia assessor or GIS parcel record was queried, so 68 of 70 research leads carry no parcel identifier.
- the broad discovery sweep remains incomplete for Georgia, so remaining county portals could only be reached by guessing URLs.
Selected records
- Microsoft Data Center Project Information — Town of Tyrone · Town of Tyrone
- Whitfield County Tax Parcel Information — parcel 13-060-01-000 (realkey 31339) · Whitfield County, Georgia (GIS / Tax Assessor)
- Project Camellia — OpenAI Data Center, Effingham County · Effingham County, Georgia
- tax abatement development agreements — Partly checked
- No Georgia development authority agreement, bond resolution or superior court validation order was retrieved; the Clayton County award is documented only through a news account.
- The Fayette County Development Authority incentives page could not be retrieved during review.
- The $1.2 billion Integra SPV equipment-bond validation reported for CoreWeave Dalton II in June 2026 was not obtained, so the research lead has no agreement in evidence.
- The Town of Tyrone record affirmatively states no abatement was requested or offered there, which is the only abatement fact confirmed from a government source in the current research record.
Selected records
- Clayton County, Ga., Agency Approves Tax Break for Data Center · Government Technology (republishing The Atlanta Journal-Constitution)
- operator disclosures — Checked
- DC BLOX's Rockdale page could not be retrieved and T5's Atlanta IV page was unavailable, so the 154 critical IT MW and 200 MW phase-one figures noted by the dataset are not recorded.
- Microsoft, QTS, Switch, STACK, CoreSite, Digital Realty, Flexential, Aligned, Edged, Vantage, DataBank, Northern Data, Prologis, CyrusOne and Serverfarm pages were not individually read.
- Oracle and Apple disclosures were not checked for Georgia at all.
- Amazon's release gives no site, acreage or capacity for either Georgia county.
Selected records
- open datasets directories — Checked
- Compute Atlas source URLs were followed only for the Whitfield parcel, the SELC letter, the Clayton and Coweta news items and the operator pages; most of its press links were not yet reviewed directly.
- The dataset notes a QTS Atlanta DC2 building record that is not in this state extract and therefore is not a research lead here.
- No unlicensed directory was used, so Georgia facilities absent from Compute Atlas — smaller colocation sites in particular — are missing.
Selected records
- Compute Atlas — Georgia facility extract, snapshot 71df1457 · Compute Atlas (Edward Kubiak)
- historical closures withdrawals names — Checked
- No county or city record of any Georgia withdrawal or denial was retrieved; both documented ones rest on news accounts.
- A report that the Temple / Project Bus developer pulled its proposal appears in the dataset's own source list but was never opened, leaving an unverified lead's status in conflict.
- Older Georgia closures, demolitions and acquisitions before 2024 were not searched.
- Newton County and Floyd County data center moratoriums referenced in the dataset's sources were not retrieved.
Selected records
- Proposal for Clayton County data center withdrawn · Atlanta News First
- Project Oak data center denied by commissioners · The Newnan Times-Herald
- news and other discovery — Partly checked
- Only one background article was read; the large volume of Georgia data center reporting seen in dataset source lists was not yet reviewed directly.
- Advocacy and research trackers other than the SELC enforcement letter were not consulted.
Selected records
- Where Coweta's five proposed data centers stand · The Newnan Times-Herald