Missouri data centers: what the public record shows.
Selected source-linked records are published below. This is not a complete inventory of Missouri data centers.
Explore Missouri
Map, listings and checked facts.
Start with 18 licensed source leads, then inspect the separate public-evidence layer below. Licensed rows are not independently verified and are not a statewide census.
Missouri map
Reported locations in Missouri
18 licensed rows · 12 source localities · 3 map targets
Browse 3 mapped areas as links
Map sources and method
The state outline is adapted from the U.S. Census Bureau 2025 cartographic boundary file. Facility coordinates are adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Outline and markers use one geographic projection before any explicitly disclosed readability offset. Exact singleton source anchors are never moved. A one-kilometre boundary tolerance prevents the simplified 1:20,000,000 outline from hiding legitimate border-area source points; farther conflicts are disclosed, not clamped. DataCenterData groups source-reported city coordinates only within a bounded map radius; the outline does not validate a facility record.
Browse all 18 rows below. Licensed rows are not independently verified and remain separate from the checked public-evidence layer.
-
Armory Innovation District Data Center
Contour / TerraWatt (with Steadfast City, THO Investments, ARCO, Lewis Rice)
Adjacent to The Armory, Midtown (former Macy's/Famous-Barr warehouse site) · St. Louis · Missouri
source-reported permittedPlanned 120 MWSource updated 24 August 2026approximate locationView facility →dcd-dir-000099 -
source-reported under constructionCapacity not statedSource updated 7 July 2026exact locationView facility →
dcd-dir-000141
Missouri evidence at a glance
A few checked sites
Selected public evidence, not a statewide census. Each row shows whether it is independently source-linked, attributed, or unresolved; licensed leads remain separate.
- Published project / campus
- 1
- Published facility / building
- 0
- Attributed or unresolved rows
- 0
- Licensed directory leads
- 18 not independently verified
- Capacity boundary stated
- 0 of 1 published DataCenterData rows
- Review timing
- Audit through 12 September 2026 · next 12 March 2027
No Missouri Works or Chapter 100 award list was opened, and no state data center sales tax exemption register was located.
Browse all 18 Missouri licensed leads → · Why these counts differ →
Projects
1 project record. Names are as they appear on each record page.
| Rifle Range Road Data Center Project | constructionproject · county-reported · 21 May 2026 | UnknownNo independently supported figureThe opened County update publishes no critical-IT, facility-load, utility-service, utility-request, generation or measured-load figure. | Webster County Commission — Data Center Update — May 21 →Gov. record |
Where the records were checked
Statewide audit pending
A few checked sites
This is not a list of every data center in the state, and the number here is not a count of them. There are almost certainly more.
Statewide coverage is not complete. The records below are sourced; a full statewide count has not been published.
State research audit window ended 12 September 2026. Individual records and claims below show their own evidence dates and may be newer.
Next scheduled review: 12 March 2027.
1 independently source-linked project/campus record; 0 independently source-linked facility/building records; 0 attributed or unresolved rows. These counts use different units and must not be added together.
Source families checked, selected records and remaining gaps
These notes name selected records, say which kinds of public evidence were checked and show what remains missing. They do not add anything to the published counts.
- economic development incentives — Partly checked
- No Missouri Works or Chapter 100 award list was opened, and no state data center sales tax exemption register was located.
- The Montgomery County tax abatement framework for AWS and the Google PILOT terms were seen only in search results, not in a county record.
Selected records
- Missouri Secures $15 Billion Investment from Google in Montgomery County · Office of Governor Mike Kehoe, State of Missouri
- Lambda to establish AI factory facility in Kansas City · Missouri Department of Economic Development
- utility commission large load — Partly checked
- EFIS has no keyword search I could reach without interactive use, so only dockets surfaced by earlier searching were opened.
- No Evergy large-load tariff, special contract or electric service agreement docket was located.
- The Ameren CCN docket EA-2026-0058 for Montgomery and Callaway transmission upgrades was opened only at the docket-sheet level; its filings were not read.
Selected records
- Ameren Missouri Motion for Protective Order, File No. ER-2026-0291 · Missouri Public Service Commission
- EFIS docket sheet EA-2026-0058, Ameren Missouri CCN for transmission upgrades in Montgomery and Callaway Counties · Missouri Public Service Commission
- EFIS docket sheet EO-2026-0037, Ameren Missouri special contemporary resource planning issues · Missouri Public Service Commission
- environmental construction permits — Partly checked
- The issued air permit index serves 40 alphabetical entries per page with no keyword filter reachable without interactive use, so no data center construction permit was retrieved for any Missouri research lead.
- Water withdrawal, wastewater and land disturbance permits were not searched.
Selected records
- Data Centers · Missouri Department of Natural Resources
- Issued Air Permits · Missouri Department of Natural Resources
- municipal planning assessor gis — Partly checked
- The City of Warrenton agenda and minutes page serves no documents, so the Crusoe conditional use permit and site plan record was not read.
- No City of Independence record for the Nebius project was retrieved.
- No Missouri county assessor or GIS parcel record was opened, so no research lead carries a parcel identifier.
- The Montgomery County Commission administrative review for Project Green and Project Spade was not retrieved.
Selected records
- Kansas City Ordinance 210841, preliminary plat for Zone 3 of Golden Plains Technology Park · City Clerk, Kansas City, Missouri
- Webster County Commission – Data Center Update – May 21 · Webster County, Missouri
- City of Warrenton Meeting Agendas & Minutes · City of Warrenton, Missouri
- tax abatement development agreements — Partly checked
- The Chapter 100 bond documents and the actual development agreements behind Project Mica and Project Kestrel were not retrieved.
- The Montgomery County AWS tax abatement framework approved in December 2025 and the Google PILOT terms were not retrieved.
Selected records
- Project Mica · Port Authority of Kansas City (Port KC)
- $100 Billion Data Center Development to bring Infrastructure, Investment and Jobs to the Northland · Port Authority of Kansas City (Port KC)
- operator disclosures — Partly checked
- Amazon, Google, Meta, Nebius, Lambda, QTS, TierPoint, Netrality and Patmos disclosure pages were not yet reviewed directly.
- the current review did not include a broad discovery sweep before this family could be searched properly, so it rests on direct URL fetches only.
Selected records
- Crusoe corporate site · Crusoe Energy Systems
- open datasets directories — Checked
- No directory listing (Data Center Map, Baxtel, datacenters.com) was opened.
Selected records
- Compute Atlas state extract for Missouri (19 records) · Compute Atlas
- historical closures withdrawals names — Partly checked
- The KSDK article covering the Franklin County rejection of the Crooked Creek data center could not be retrieved during review, so that rejection is recorded only as an access failure and has no research lead.
- No Kansas City Plan Commission case file was retrieved for the Quality Hill denial.
- Renames, acquisitions and closures of Missouri colocation facilities were not researched.
Selected records
- news and other discovery — Partly checked
- Most news leads in the Compute Atlas extract were not yet reviewed directly.
- The KSDK Franklin County article was blocked.
Selected records
- Warren County Record: Warrenton Planning and Zoning approves data center site plan, conditional use · Warren County Record
- ABC 17 News: Montgomery County approves land for two large-scale projects on Amazon data center campus · ABC 17 News (KMIZ)
- KSHB 41: Nebius breaks ground on 45-acre AI data center in Independence amid community opposition · KSHB 41 (Scripps)