expansion design · IN · coreweave-hammond
OutdatedSaid by City of Hammond (government) on 2025-06-10 in City of Hammond.
Checked 11 September 2026
450,000 square feet; 180 MW; contemplated 20-year CoreWeave lease
What the evidence supports
Development agreement expired; expansion not delivered.
Still unknown
Exact unsatisfied milestones.
Evidence details
-
City of Hammond → Gov. record
Exact location https://www.gohammond.com/hammond-approves-development-agreement-for-new-data-center/
What it supports Approval, proposed building, tenant, power requirement and contingencies.
-
Hammond Common Council minutes, 9 June 2025 → Gov. record
Exact location pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
What it supports Proposal, contemplated lease, jobs, tax terms, community payments and explicit power-agreement gating.
Counterevidence
None recorded.
Next check
replacement proposal, new NIPSCO docket or new development agreement
History
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Expansion design
Field Expansion design
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Data + actions
CoreWeave / Digital Crossroads expansion · Linked record
Suggest a correction → Claim ID claim:coreweave-hammond:expansion-design and the page are prefilled. Accepted material corrections appear publicly on Changes.