Facts at a glance
- Record ID
amazon-bwi150-frederick-campus- Record type
- campus
- Developer
- Not named in the cited records
- Operator
- Not named in the cited records
- Owner
- Owner of record not established
- Tenant
- Not named in the cited records
- Capacity
- Unknown No independently supported figure
The permit covers backup generators. Their ratings are not critical IT capacity, utility service, measured load or evidence that the campus is operating. - Location
- 3250 Digital Drive, MD
County: Frederick County
exact — The permit gives Frederick, MD 21703 as the locality label. It does not establish that the site is incorporated within the City of Frederick, and no parcel crosswalk is published here. - Physical scale
- Physical scale: No building or operating-facility count is added to the public totals from this approval record.
What the sources support
The Maryland Department of the Environment issued an emergency-generator construction permit for Amazon Data Services' BWI-150–BWI-153 campus on March 25, 2026. The permit establishes an approval milestone; it does not establish campus construction, operation or critical IT capacity.
Definitions: record units · roles · capacity boundaries · lifecycle stages.
What remains unknown
- incorporated city boundary
- parcel crosswalk
- land owner
- developer
- operator
- critical IT capacity
- utility service capacity
- campus construction evidence
- opening or completion date
Sources
-
MDE Permit to Construct — Amazon BWI-150 through BWI-153 →Gov. record
Exact location PDF pp. 1–2, construction-permit stamp; control B-08076; premises 021-0809; AI 185075
What it supports Amazon Data Services, BWI-150 through BWI-153 campus identity, issued emergency-generator construction permit and 3250 Digital Drive address.
-
Maryland Department of the Environment approves air permit for Frederick data center →Gov. record
Exact location Headline and opening paragraph; emergency-generator use paragraph
What it supports Final air-permit determination, applicant, address and backup-generator purpose. It does not establish campus operation.
-
Frederick Data Center sampling and reports →Gov. record
Exact location Quantum Maryland / Quantum Frederick section; 2026 Documents
What it supports Amazon project identity at 3250 Digital Drive and the issued BWI permit's place in the larger Quantum Frederick site. No canonical parent relationship is inferred.
Record history
Record history · 25 March 2026 · DataCenterData review
amazon-bwi150-frederick-campus → Record
Why MDE issued the emergency-generator air construction permit.
Evidence No additional evidence link; see the linked record or claim.
DataCenterData record added · 13 September 2026 · DataCenterData review
amazon-bwi150-frederick-campus → Publication
Why Added as one permit-approved campus after a fresh review of the issued permit and MDE pages; generator ratings and broader-site relationships were not promoted.
Evidence No additional evidence link; see the linked record or claim.
Data + actions
Permanent link for citing this record →
Suggest a correction → Record ID amazon-bwi150-frederick-campus and the page are prefilled. Accepted material corrections appear on Changes.