Facts at a glance
- Record ID
project-baccara- Record type
- project
- Developer
- Takanock, LLC
- Operator
- Not named in the cited records
- Owner
- Owner of record not established
- Tenant
- Not named in the cited records
- Capacity
- 700 MW onsite generation planned · site scope
Approximately 700 MW of planned natural-gas generation for the data center and regional grid; not critical IT capacity, utility demand or measured load. - Location
- Maricopa County, AZ
approximate — Arizona Corporation Commission describes an industrial area north of Luke Air Force Base near Olive Avenue and the Bullard Avenue alignment. No reconciled parcel or occupied street address is published here. - Physical scale
- Physical scale: Two planned data-center buildings. Planned buildings are not operating buildings.
What the sources support
The data-center project remains proposed. The Arizona Corporation Commission voted on February 4, 2026 to approve a Certificate of Environmental Compatibility for Baccara Power, LLC's planned generation and interconnection, but expressly said this was not approval of the data center; Maricopa County and Luke Air Force Base approvals were still pending. No construction record was reviewed.
Definitions: record units · roles · capacity boundaries · lifecycle stages.
What remains unknown
- street address
- parcel identifiers
- owner
- operator
- critical IT capacity
- utility service capacity
- construction evidence
- Maricopa County approval
- Luke Air Force Base approval
Sources
-
Arizona Corporation Commission February 4, 2026 Open Meeting Highlights →Gov. record
Exact location Utilities section, Baccara Power, LLC
What it supports Project identity, developer, county, generation-certificate approval, planned building count, generation scope and outstanding approval boundary.
Record history
Record history · 4 February 2026 · DataCenterData review
project-baccara → Record
Why Arizona Corporation Commission approved the generation and interconnection Certificate of Environmental Compatibility; it did not approve the data center itself.
Evidence No additional evidence link; see the linked record or claim.
DataCenterData record added · 13 September 2026 · DataCenterData review
project-baccara → Publication
Why Added as a proposed data-center project after a second review of the Commission source; the separate generation-certificate approval is preserved without promoting the project lifecycle.
Evidence No additional evidence link; see the linked record or claim.
Data + actions
Permanent link for citing this record →
Suggest a correction → Record ID project-baccara and the page are prefilled. Accepted material corrections appear on Changes.