Facts at a glance
- Record ID
project-jupiter-santa-teresa- Record type
- campus
- Developer
- STACK Infrastructure and BorderPlex Digital Assets
- Operator
- Not named in the cited records
- Owner
- Owner of record not established
- Tenant
- Not named in the cited records
- Capacity
- 2.462 GW onsite generation planned · site scope
Requested YGI Microgrid generation in a pending air-permit application; not critical IT load, utility demand or issued capacity. - Location
- Doña Ana County, NM
approximate — Santa Teresa Industrial Park in unincorporated Doña Ana County; no primary-source parcel or campus coordinate established. - Physical scale
- Physical scale: Four anticipated data-center facilities in Ordinance 367-2025.
What the sources support
Doña Ana County's April 14, 2026 update describes the data-center campus as under construction in the Santa Teresa Industrial Park. No reviewed source establishes operation.
Definitions: record units · roles · capacity boundaries · lifecycle stages.
What remains unknown
- street address
- parcel
- owner
- operator
- critical IT capacity
- utility service capacity
- issued microgrid permit
Sources
-
Doña Ana County Ordinance No. 367-2025 →Gov. record
Exact location Recorded p. 1, lines 5-25; Instrument 2520581
What it supports Project identity, county and four anticipated facilities.
-
Doña Ana County Project Jupiter update →Gov. record
Exact location Opening project-description paragraph
What it supports Construction status and Santa Teresa Industrial Park location.
-
NMED amended hearing notice, AQB 26-57(P), NSR 10883 →Gov. record
Exact location p. 1, Brief Description of Permit Application
What it supports Related microgrid applicant, proposed generation capacity and location; not an issued permit.
Record history
Record history · 22 September 2025 · DataCenterData review
project-jupiter-santa-teresa → Record
Why County recorded Ordinance 367-2025.
Evidence No additional evidence link; see the linked record or claim.
Record history · 14 April 2026 · DataCenterData review
project-jupiter-santa-teresa → Record
Why County described the campus as under construction.
Evidence No additional evidence link; see the linked record or claim.
Record history · 12 August 2026 · DataCenterData review
project-jupiter-santa-teresa → Record
Why NMED noticed a hearing on the pending 2,462 MW generation application.
Evidence No additional evidence link; see the linked record or claim.
Data + actions
Permanent link for citing this record →
Suggest a correction → Record ID project-jupiter-santa-teresa and the page are prefilled. Accepted material corrections appear on Changes.