Facts at a glance
- Record ID
qts-eagle-mountain-campus- Record type
- campus
- Developer
- QTS
- Operator
- Not named in the cited records
- Owner
- Owner of record not established
- Tenant
- Not named in the cited records
- Capacity
- Unknown No independently supported figure
- Location
- Eagle Mountain, UT
County: Utah County
approximate — City updates place this campus west of Meta. The 2024 RDA packet's Sweetwater #3 plan lists the historical QTS I/II parcels in Utah County; current parcel and street-address reconciliation remains open. - Physical scale
- Physical scale: The April 2026 city update describes five planned first-phase buildings on approximately 193 acres; it does not establish five operating buildings.
What the sources support
Eagle Mountain City's April 20, 2026 update documents the first building's structural topping-out on April 17 and says interior and remaining-campus construction will continue. This establishes a construction milestone, not an opening.
Definitions: record units · roles · capacity boundaries · lifecycle stages.
What remains unknown
- current street address
- current parcel crosswalk
- operator
- critical IT capacity
- utility service capacity
- opening date
- relationship to other QTS Eagle Mountain/Fairfield and North Virtual Drive projects
Sources
-
Eagle Mountain City Celebrates Major Milestone with QTS Topping Out Ceremony →Gov. record
Exact location Article body, opening two paragraphs and final paragraph
What it supports April 17 structural milestone, continuing construction and planned first-phase scale.
-
Construction restarts on QTS Data Center in Eagle Mountain →Gov. record
Exact location Article body, opening two paragraphs and construction-resumption paragraph
What it supports QTS developer identity, campus west of Meta and resumed construction.
-
Eagle Mountain Redevelopment Agency August 20, 2024 meeting packet →Gov. record
Exact location PDF p. 75 / printed p. 6, Amended Sweetwater Industrial Park CRA #3 plan, Table 1 and boundary description; packet cover posting certificate
What it supports Historical QTS I/II parcel grouping, county and location context only. The packet is not proof that a proposed agreement was executed.
Record history
Record history · 29 October 2025 · DataCenterData review
qts-eagle-mountain-campus → Record
Why City reported that campus construction had resumed.
Evidence No additional evidence link; see the linked record or claim.
Record history · 17 April 2026 · DataCenterData review
qts-eagle-mountain-campus → Record
Why City subsequently documented structural topping-out of the first building; additional construction remained.
Evidence No additional evidence link; see the linked record or claim.
DataCenterData record added · 12 September 2026 · DataCenterData review
qts-eagle-mountain-campus → Publication
Why Added as a bounded construction-stage campus record after a second review of the cited Eagle Mountain City sources.
Evidence No additional evidence link; see the linked record or claim.
Data + actions
Permanent link for citing this record →
Suggest a correction → Record ID qts-eagle-mountain-campus and the page are prefilled. Accepted material corrections appear on Changes.