Construction reported on 17 April 2026: QTS Eagle Mountain Campus (Eagle Mountain, UT) — city press release dated 20 April 2026
Eagle Mountain City reported that on April 17, 2026 crews placed the final beam on the first QTS data center building in Eagle Mountain, and that construction will continue on interior systems and the remaining buildings.
- Event date
- Article text 'On Friday, April 17, crews placed the final beam'; year from the April 20, 2026 dateline.
- Source dated
- Article dateline 'April 20, 2026'.
- Source accessed
- Retrieved by DataCenterData; not an event date.
- Added to Latest updates
- When this entry entered the updates log; not an event date.
- Event type
- Construction reported · Construction
- Evidence basis
- Official record · Eagle Mountain City
- Confidence
- HighOfficial city publication; dated construction milestone; exact campus link.
- State
- Utah
- Linked records
- QTS Eagle Mountain Campus
qts-eagle-mountain-campus - Linked claims
- None linked
What the source says
On Friday, April 17, crews placed the final beam on the first QTS data center building in Eagle Mountain. This step, known as a “topping out,” marks the completion of the building’s structural framework.
Where: Article body, first paragraph
Source: Eagle Mountain City Celebrates Major Milestone with QTS Topping Out Ceremony
Internet Archive copy (captured 19 August 2026)
What this does not establish
- Building completion (structural topping-out only)
- Energization or operation
Still unknown
- Completion or opening date of the first building
- IT capacity and operator/tenant
- Progress on the remaining four planned buildings
Identifiers
Event ID 81aa2655060fc9467da9fd15cc2a3f4b510599e897caa377f63be610c9f7d056. The ID is derived from the event itself and never changes. A later correction would be published as a separate, linked entry.