Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.
Facility and project events
Construction reportedOfficial recordUtah
Construction reported on 17 April 2026: QTS Eagle Mountain Campus (Eagle Mountain, UT) — city press release dated 20 April 2026
Eagle Mountain City reported that on April 17, 2026 crews placed the final beam on the first QTS data center building in Eagle Mountain, and that construction will continue on interior systems and the remaining buildings.
- Event date
- Source dated
- Added to Latest updates
Record: QTS Eagle Mountain CampusSource: Eagle Mountain City Celebrates Major Milestone with QTS Topping Out CeremonyArchived copy
Evidence updates
Evidence updateDataCenterData publicationUtah
Evidence record published: QTS Eagle Mountain Campus (Eagle Mountain, UT)
- Published on DataCenterData
How to read the dates
- Event date
- When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
- Source dated
- The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
- Source accessed
- When DataCenterData retrieved the source. Shown on each event page.
- Added to Latest updates
- When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.