Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.

Facility and project events

  1. Final plat approvedOfficial recordLouisiana

    Final plat approved on 18 March 2026: Technology Park Data Center Project (LA) — parish government release dated 20 March 2026

    The Bossier Parish Police Jury, at its March 18, 2026 regular agenda meeting, unanimously approved the Benton Metropolitan Planning Commission's final plat recommendation for the Technology Park supporting the new Amazon data center.

    Event date
    Source dated
    Added to Latest updates

Evidence updates

No evidence updates for Louisiana in this log.

All latest updates →

How to read the dates
Event date
When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
Source dated
The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
Source accessed
When DataCenterData retrieved the source. Shown on each event page.
Added to Latest updates
When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.