Latest updates · 4 dated events · log last updated 21 September 2026
Virginia data center updates
Dated facility and project events and DataCenterData evidence updates for Virginia. Not a complete record of activity in Virginia.
Facility and project events
Permit issuedOfficial recordVirginia
Botetourt County permit issued in August 2026: Google Data Center Campus — Botetourt Center at Greenfield (VA) — land disturbance permit for Mass Grading Package No. 1 (phased grading)
Botetourt County reported that Google had received a County Land Disturbance Permit, after the County completed review of Mass Grading Package No. 1, allowing phased grading on its 312-acre site in the Botetourt Center at Greenfield.
- Event date
- Source dated
- Added to Latest updates
Record: Google Data Center Campus — Botetourt Center at GreenfieldSource: Grading to Begin for Google Data Center ProjectArchived copy
Construction reportedOfficial recordVirginia
Construction reported in July 2026: Google Bermuda Hundred Data Center Campus (VA) — county project status table dated July 2026
Chesterfield County's 'Data Center Project Status as of July 2026' table lists Peanut LLC at 2100 Bermuda Hundred Road as 'Under construction; three buildings'.
- Event date
- Source dated
- Added to Latest updates
Record: Google Bermuda Hundred Data Center CampusSource: Data Centers — Chesterfield County (Data Center Project Status as of July 2026)Archived copy
Rezoning approvedOfficial recordVirginia
Rezoning approved on 28 May 2025: Google Watkins Centre Data Center Project (VA) — county board minutes dated 28 May 2025
The Chesterfield County Board of Supervisors approved rezoning Case 25SN1040 (Watkins Centre South; 349.97 acres (8 parcels) known as 750 Watkins Centre Parkway et al.) from Agricultural (A) and General Industrial (I-2) to General Industrial (I-2), subject to conditions, by a 5-0 vote on May 28, 2025.
- Event date
- Source dated
- Added to Latest updates
Record: Google Watkins Centre Data Center ProjectSource: Chesterfield County Board of Supervisors Minutes — May 28, 2025Archived copy
Rezoning approvedOfficial recordVirginia
Rezoning approved on 28 May 2025: Google Upper Magnolia Green Data Center Project (VA) — county board minutes dated 28 May 2025
The Chesterfield County Board of Supervisors approved rezoning Case 25SN1038 (Upper Magnolia Green West Tract A & Tract B; 979.23 acres fronting Moseley Road and Mount Hermon Road) from Agricultural (A) and General Industrial (I-2) to General Industrial (I-2), subject to conditions, by a 5-0 vote on May 28, 2025.
- Event date
- Source dated
- Added to Latest updates
Record: Google Upper Magnolia Green Data Center ProjectSource: Chesterfield County Board of Supervisors Minutes — May 28, 2025Archived copy
Evidence updates
Evidence updateDataCenterData publicationVirginia
Evidence record published: Thornburg Industrial Park 2 (VA)
- Published on DataCenterData
Evidence updateDataCenterData publicationVirginia
Evidence record published: Massaponax Tech Campus (VA)
- Published on DataCenterData
Evidence updateDataCenterData publicationVirginia
Evidence record published: Mineral Gap Data Center (Wise, VA)
- Published on DataCenterData
Evidence updateDataCenterData publicationVirginia
Evidence record published: EdgeCore Shannon Hill Data Center Project (VA)
- Published on DataCenterData
Evidence updateDataCenterData publicationVirginia
Evidence record published: Pairmont Data Center Campus (VA)
- Published on DataCenterData
Evidence updateDataCenterData publicationVirginia
Evidence record published: Solis Arx / Fluidstack Progress Park Project (VA)
- Published on DataCenterData
How to read the dates
- Event date
- When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
- Source dated
- The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
- Source accessed
- When DataCenterData retrieved the source. Shown on each event page.
- Added to Latest updates
- When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.